How Genesys Cloud calculates historical shrinkage
Series: Historical shrinkage
Previous suggested step: Navigate the historical shrinkage view
Genesys Cloud calculates total logged hours for actual shrinkage as the sum of activity category durations and time-off durations. The following activity categories are excluded from the calculation unless the activity occurs within a scheduled shift:
- Offline
- Away
- Idle
Total logged hours = All activity categories duration (Except offline or away or idle. These are included only if the activity lies within the shift) + time-off duration.
Shrinkage calculation by activity category
To view details on a particular activity category that are included in shrinkage, click the corresponding section.
Note: Genesys Cloud calculates shrinkage only for those activities for which Shrinkage Activity is selected in the activity code configuration. For more information, see Configure activity codes.
Notes:
- Paid or unpaid hours are determined from the activity code configuration. For more information, see Configure activity codes.
- If an agent modifies the Paid/Unpaid toggle for an activity code when they create or update their work plan or from the Schedule view, Genesys Cloud does not consider the modification and the same displays as a discrepancy in the Paid/Unpaid Shrinkage field.